Reason for Work
The following categories have been included in the list of programmed schemes to identify the factors supporting their inclusion in the programme
A. Identified through a condition survey process
B. Identified through accident investigations as being an accident cluster site or subject to low Sideway-Force Coefficient Routine Investigation Machine (SCRIM).
C. Subject to high maintenance remedial works
D. Route identified within condition surveys and forming part of strategic development scheme
Note
Whilst every effort has been made to achieve a definitive programme that will provide effective management of the highway assets, it may be subject to change in content and detail throughout the year. Such changes can arise from the need to address unforeseen maintenance demands arising during the year i.e emergency public utilities works and budget adjustments.
Additional Structural Footway Improvements 2008/09
| Location |
Reason for Work |
Reason for Work |
Estimated cost (£) |
| A525 |
Bangor on Dee to Hollybush |
A |
£20,820 |
| |
Abbeygate walk, Bangor on Dee |
A |
£28,740 |
| |
Queen Street, Ruabon |
A |
£2,460 |
| A525 |
Kingsmills Road, Hightown |
A |
£10,980 |
| |
Celmar Grove, Rhostyllen |
A |
£9,500 |
| |
Vinegar Hill, Rhos |
A |
£9,500 |
| |
B5605 Wrexham Road, Pentrbychan |
A |
£27,000 |
| |
Heol Offa, Johnstown |
A |
£9,000 |
| |
Larchwood Road (LEFT AND RIGHT) |
A |
£9,500 |
| |
Ffordd Alun (RHS) |
A |
£10,260 |
| |
Brecon Close (LEFT AND RIGHT) |
A |
£4,788 |
| |
Lodge Road RHS |
A |
£3,420 |
| |
Weston Drive RHS |
A |
£8,588 |
| A525 |
A525 Cross lanes to Bangor-on-Dee |
A |
£38,000 |
| A534 |
Holt road by Gredington |
A |
£11,400 |
| |
Heol Glyndwr, Coedpoeth |
A |
£17,750 |
| |
Waverley Crescent, Brynteg |
A |
£21,000 |
| |
Rose Hill, Brynteg |
A |
£13,000 |
| |
Mayflower Drive, Marford |
A |
£8,950 |
| |
Various Link Footpaths |
A/C |
£30,000 |
| |
|
Total Estimated Cost |
£294,656 |